Yes, normally you must find out the corresponding test standards about your products, but from your description about the dielectric test, I guess this test should be initiated on the production line.so follow the steps as follows:
1.check the related standards and find the related requirements for your products, such as follows:
on the production line(routint test): 1.2k for 2 seconds, with the leakage current 3mA
for type test:1kV for i minute, with the leakage current 3mA
2. set your own test instructions, and specify the test procedure, maybe, your test requirements are more severe than the standards' requirements, that's also ok for robustness.
3. do the test, if breakdown, then reject, if not, accept..
normally, for UL, there is no requirement for the leakage current, and as per the experience, 10mA, but for other parties, 3.5~10mA is recommended... |
|