There shall be no insulation breakdown during the test.
Insulation breakdown is considered to have occurred when the current that flows as a result ofthe application of the test voltage rapidly increases in an uncontrolled manner, that is the insulation does not restrict the flow of the current. Corona discharge or a single momentary flashover is not regarded as insulation breakdown.作者: ehfhhe 时间: 2011-9-26 22:39
自从VDE自己进行厂检后,问题就很多~~好麻烦作者: pxcuag 时间: 2011-9-26 22:40
审查员不认为在制程中的漏电流不符合标准,而是认为我司在仪器的功能检查时使用的样品不对。我司的改善对策是:并联个电阻,粗略计算出漏电流的数值。作者: MS168 时间: 2011-9-26 23:19